Exam Overview

The exam for the PMI CAPM certification contains 150 multiple-choice questions, including 13 unscored items. The unscored questions will not influence on the final result and are included in the test for research purposes. The candidate will be given 3 hours to answer all the questions. The exam is available in multiple languages, including Arabic, Traditional Chinese, Simplified Chinese, Brazilian Portuguese, Japanese, Korean, French, German, English, Hebrew, Italian, Russian, Spanish, and Turkish. You can take it either as an online proctored option or at any authorized Pearson VUE testing center. The exam cost for the PMI members is $225, while for the non-members, it is $300. Every 3 years, the certificate holders should earn 15 PDUs to maintain their certification status and pay a renewal fee of $60 (members) or $150 (non-members).

 

NEW QUESTION 178
Outputs from constituent processes might be used as:

  • A. Inputs to other processes.
  • B. Identification of project tasks.
  • C. Indicators to eliminate project redundancies.
  • D. Proof of process completion.

Answer: A

Explanation:
Section: Volume E
Explanation

 

NEW QUESTION 179
A change log for communications can be used to communicate to the appropriate stakeholders that there are changes:

  • A. In the scope verification processes.
  • B. And their impact to the project in terms of time, cost, and risk.
  • C. To the risk register.
  • D. To the project management plan.

Answer: B

Explanation:
Explanation/Reference:
Explanation:
4.5.3.2 Change Log
A change log is used to document changes that occur during a project. These changes and their impact to the project in terms of time, cost, and risk, are communicated to the appropriate stakeholders. Rejected change requests are also captured in the change log.
13.3.1.3 Change Log
Described in Section 4.5.3.2. A change log is used to document changes that occur during a project.
These changes-and their impact on the project in terms of time, cost, and risk-are communicated to the appropriate stakeholders.

 

NEW QUESTION 180
Which process involves the creation of a document that provides the project manager with the authority to apply resources to a project?

  • A. Define Activities
  • B. Develop Project Management Plan
  • C. Direct and Manage Project Work
  • D. Develop Project Charter

Answer: D

Explanation:
Explanation/Reference:
Explanation:
Process: 4.1. Develop Project Charter
Definition: The process of developing a document that formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities.
Key Benefit: The key benefit of this process is a well-defined project start and project boundaries, creation of a formal record of the project, and a direct way for senior management to formally accept and commit to the project.
Inputs
1. Project statement of work
2. Business case
3. Agreements
4. Enterprise environmental factors
5. Organizational process assets
Tools & Techniques
1. Expert judgment
2. Facilitation techniques
Outputs
1. Project charter

 

NEW QUESTION 181
Project Stakeholder Management focuses on:

  • A. project staff assignments
  • B. managing conflicting interests
  • C. communication methods
  • D. project team acquisition

Answer: B

Explanation:
Explanation/Reference:
Explanation:
PROJECT STAKEHOLDER MANAGEMENT
Project Stakeholder Management includes the processes required to identify the people, groups, or organizations that could impact or be impacted by the project, to analyze stakeholder expectations and their impact on the project, and to develop appropriate management strategies for effectively engaging stakeholders in project decisions and execution. Stakeholder management also focuses on continuous communication with stakeholders to understand their needs and expectations, addressing issues as they occur, managing conflicting interests and fostering appropriate stakeholder engagement in project decisions and activities. Stakeholder satisfaction should be managed as a key project objective

 

NEW QUESTION 182
Documented identification of a flaw in a project component together with a recommendation is termed a:

  • A. defect repair.
  • B. non-conformance report,
  • C. preventive action.
  • D. corrective action.

Answer: A

Explanation:
Section: Volume D

 

NEW QUESTION 183
A project team of telecommuters located in three different time zones regularly misses project deadlines. Daily meetings often start and end with the same person talking and the rest of the team listening. The project manager determines that communication among team members must be addressed.
What communication step is missing from the daily meetings?

  • A. Interpersonal communication
  • B. Pull communication
  • C. Push communication
  • D. Feedback/response communication

Answer: D

Explanation:
Section: Volume E

 

NEW QUESTION 184
The process of monitoring the status of the project to update project progress and manage changes to the schedule baseline is:

  • A. Control Schedule.
  • B. Quality Control.
  • C. Develop Schedule.
  • D. Perform Integrated Change Control.

Answer: A

 

NEW QUESTION 185
A given schedule activity is most likely to last four weeks. In a best-case scenario, the schedule activity is estimated to last two weeks. In a worst-case scenario, the schedule activity is estimated to last 12 weeks.
Given these three estimates, what is the expected duration of the activity?

  • A. Four weeks
  • B. Six weeks
  • C. Five weeks
  • D. Three weeks

Answer: C

Explanation:
Explanation/Reference:
Explanation:
6.5.2.4 Three-Point Estimating
The accuracy of single-point activity duration estimates may be improved by considering estimation uncertainty and risk. This concept originated with the program evaluation and review technique (PERT).
PERT uses three estimates to define an approximate range for an activity's duration:
Most likely (tM). This estimate is based on the duration of the activity, given the resources likely to be

assigned, their productivity, realistic expectations of availability for the activity, dependencies on other participants, and interruptions.
Optimistic (tO). The activity duration based on analysis of the best-case scenario for the activity.

Pessimistic (tP). The activity duration based on analysis of the worst-case scenario for the activity.

Depending on the assumed distribution of values within the range of the three estimates the expected duration, tE, can be calculated using a formula. Two commonly used formulas are triangular and beta distributions.
The formulas are:
Triangular Distribution. tE = (tO + tM + tP) / 3

Beta Distribution (from the traditional PERT technique). tE = (tO + 4tM + tP) / 6

Duration estimates based on three points with an assumed distribution provide an expected duration and clarify the range of uncertainty around the expected duration.
Formula:
E = (a + 4m + b) / 6
Application:
(2+ (4*4) +12)=30 /6 =5

 

NEW QUESTION 186
The process of prioritizing risks for further analysis or action is known as:

  • A. Perform Quantitative Risk Analysis.
  • B. Plan Risk Responses.
  • C. Plan Risk Management.
  • D. Perform Qualitative Risk Analysis.

Answer: D

 

NEW QUESTION 187
In which of the Risk Management processes is the project charter used as an input?

  • A. Plan Risk Responses
  • B. Perform Quantitative Risk Responses
  • C. Plan Risk Management
  • D. Implement Risk Responses

Answer: C

Explanation:
Section: Volume E
Explanation
Explanation/Reference: https://www.projectengineer.net/project-risk-management-according-to-the-pmbok/

 

NEW QUESTION 188
The completion of the project scope is measured against the:

  • A. project management plan.
  • B. project scope statement.
  • C. requirements documentation.
  • D. work performance measurements.

Answer: A

Explanation:
Section: Volume E
Explanation/Reference:
Explanation:
4.2.3.1 Project Management Plan
The project management plan is the document that describes how the project will be executed, monitored, and controlled. It integrates and consolidates all of the subsidiary plans and baselines from the planning processes.
Project baselines include, but are not limited to:
Scope baseline (Section 5.4.3.1),

Schedule baseline (Section 6.6.3.1), and

Cost baseline (Section 7.3.3.1).

Subsidiary plans include, but are not limited to:
Scope management plan (Section 5.1.3.1),

Requirements management plan (Section 5.1.3.2),

Schedule management plan (Section 6.1.3.1),

Cost management plan (Section 7.1.3.1),

Quality management plan (Section 8.1.3.1),

Process improvement plan (Section 8.1.3.2),

Human resource management plan (Section 9.1.3.1),

Communications management plan (Section 10.1.3.1),

Risk management plan (Section 11.1.3.1),

Procurement management plan (Section 12.1.3.1), and

Stakeholder management plan (Section 13.2.3.1).

Among other things, the project management plan may also include the following:
Life cycle selected for the project and the processes that will be applied to each phase;

Details of the tailoring decisions specified by the project management team as follows:

○ Project management processes selected by the project management team,
○ Level of implementation for each selected process,
○ Descriptions of the tools and techniques to be used for accomplishing those processes, and
○ Description of how the selected processes will be used to manage the specific project, including the dependencies and interactions among those processes and the essential inputs and outputs.
Description of how work will be executed to accomplish the project objectives;

Change management plan that documents how changes will be monitored and controlled;

Configuration management plan that documents how Configuration management will be performed;

Description of how the integrity of the project baselines will be maintained;

Requirements and techniques for communication among stakeholders; and

Key management reviews for content, the extent of, and timing to address, open issues and pending

decisions.
The project management plan may be either summary level or detailed, and may be composed of one or more subsidiary plans. Each of the subsidiary plans is detailed to the extent required by the specific project. Once the project management plan is baselined, it may only be changed when a change request is generated and approved through the Perform Integrated Change Control process.

 

NEW QUESTION 189
Project management processes ensure the:

  • A. performance of the project team
  • B. effective flow of the project throughout its life cycle
  • C. efficient means to achieve the project objectives
  • D. alignment with organizational strategy

Answer: B

Explanation:
Section: Volume B
Explanation
Explanation:
Project management processes. These processes ensure the effective flow of the project throughout its life cycle. These processes encompass the tools and techniques involved in applying the skills and capabilities described in the Knowledge Areas (Sections 4 through 13)

 

NEW QUESTION 190
The project manager is using co-location and providing training to the project team. On which of the following Project Resource Management processes is the project manager working?

  • A. Manage Team
  • B. Control Resources
  • C. Develop Team
  • D. Acquire Resources

Answer: C

Explanation:
Section: Volume E
Explanation/Reference: https://mymanagementguide.com/guidelines/project-management/hr-management/project-team- developing/

 

NEW QUESTION 191
Which of the following documents ate created as part of Project Integration Management?

  • A. Project charter and project management plan
  • B. Communications management plan and scope management plan
  • C. Quality management plan and risk management plan
  • D. Project scope statement and communications management plan

Answer: A

 

NEW QUESTION 192
Which Control Quality tool is also known as an arrow diagram?

  • A. Matrix diagram
  • B. Affinity diagram
  • C. Activity network diagram
  • D. Tree diagram

Answer: C

Explanation:
Section: Volume A
Explanation:
8.2.2.1 Quality Management and Control Tools
The Perform Quality Assurance process uses the tools and techniques of the Plan Quality Management and Control Quality processes. In addition, other tools that are available include (see also Figure 8-10):
Affinity diagrams. The affinity diagram is similar to mind-mapping techniques in that they are used to

generate ideas that can be linked to form organized patterns of thought about a problem. In project management, the creation of the WBS may be enhanced by using the affinity diagram to give structure to the decomposition of scope.
Process decision program charts (PDPC). Used to understand a goal in relation to the steps for getting to

the goal. The PDPC is useful as a method for contingency planning because it aids teams in anticipating intermediate steps that could derail achievement of the goal.
Interrelationship digraphs. An adaptation of relationship diagrams. The interrelationship digraphs provide a

process for creative problem solving in moderately complex scenarios that possess intertwined logical relationships for up to 50 relevant items. The interrelationship digraph may be developed from data generated in other tools such as the affinity diagram, the tree diagram, or the fshbone diagram.
Tree diagrams. Also known as systematic diagrams and may be used to represent decomposition

hierarchies such as the WBS, RBS (risk breakdown structure), and OBS (organizational breakdown structure).
In project management, tree diagrams are useful in visualizing the parent-to-child relationships in any decomposition hierarchy that uses a systematic set of rules that define a nesting relationship. Tree diagrams can be depicted horizontally (such as a risk breakdown structure) or vertically (such as a team hierarchy or OBS). Because tree diagrams permit the creation of nested branches that terminate into a single

decision point, they are useful as decision trees for establishing an expected value for a limited number of dependent relationships that have been diagramed systematically.
Prioritization matrices. Identify the key issues and the suitable alternatives to be prioritized as a set of

decisions for implementation. Criteria are prioritized and weighted before being applied to all available alternatives to obtain a mathematical score that ranks the options.
Activity network diagrams. Previously known as arrow diagrams. They include both the AOA (Activity on

Arrow) and, most commonly used, AON (Activity on Node) formats of a network diagram. Activity network diagrams are used with project scheduling methodologies such as program evaluation and review technique (PERT), critical path method (CPM), and precedence diagramming method (PDM).
Matrix diagrams. A quality management and control tool used to perform data analysis within the

organizational structure created in the matrix. The matrix diagram seeks to show the strength of relationships between factors, causes, and objectives that exist between the rows and columns that form the matrix.

 

NEW QUESTION 193
Which conflict resolution technique searches for solutions that bring some degree of satisfaction to all parties in order to temporarily or partially resolve the conflict?

  • A. Compromise/reconcile
  • B. Collaborate/problem solve
  • C. Withdraw/avoid
  • D. Force/direct

Answer: A

 

NEW QUESTION 194
Plan Risk Management is the process of defining how to:

  • A. Analyze the impact a specific risk may have on the project.
  • B. Communicate identified risks to the project stakeholders.
  • C. Address unexpected risks that may occur during a project.
  • D. Conduct risk management activities for a project.

Answer: D

 

NEW QUESTION 195
Which of the following includes how requirements activities will be planned, tracked, and reported?

  • A. Configuration management plan
  • B. Scope baseline
  • C. Requirements management plan
  • D. Schedule baseline

Answer: C

 

NEW QUESTION 196
A project manager of a civil construction project is trying to understand the local laws. What example of tailoring procurement could this best be described as?

  • A. Physical location tailoring
  • B. Compliance and governance
  • C. Availability of contractors
  • D. Complexity of procurement

Answer: A

Explanation:
Section: Volume E
Explanation

 

NEW QUESTION 197
What is the name of the statistical method that helps identify which factors may influence specific variables of a product or process under development or in production?

  • A. Design of experiments
  • B. Quality checklist
  • C. Failure modes and effects analysis
  • D. Risk analysis

Answer: A

 

NEW QUESTION 198
Which type of managers do composite organizations involve?

  • A. Project managers only
  • B. Technical managers and project managers
  • C. Functional managers and manager of project managers
  • D. Functional managers only

Answer: C

 

NEW QUESTION 199
A project is in the planning phase. The project manager is considering different elements that may influence or constrain the project.
Which of the following internal enterprise environmental factors should the project manager consider?

  • A. Legal restrictions
  • B. Market conditions
  • C. Industry standards
  • D. Employee capability

Answer: D

Explanation:
Section: Volume E
Explanation/Reference:

 

NEW QUESTION 200
According to the PMI Talent Triangle, leadership skills relate to the ability to:

  • A. guide, motivate, and direct a team to reach project goals
  • B. tailor traditional and agile tools for the project
  • C. understand the high-level overview of the organization
  • D. work with stakeholders to develop an appropriate project delivery

Answer: A

Explanation:
Section: Volume E
Explanation/Reference: https://www.pmi.org/certifications/maintain/earn-pdus/plan-development-talent-triangle

 

NEW QUESTION 201
The following chart contains information about the tasks in a project.

Based on the chart, what is the schedulevariance (SV) for Task 8?

  • A. -1,000
  • B. 1,000
  • C. -2,000
  • D. 2,000

Answer: A

 

NEW QUESTION 202
Once the make-or-buy analysis is completed, which document defines the project delivery method?

  • A. Change request
  • B. Procurement strategy
  • C. Terms of reference
  • D. Procurement statement of work (SOW)

Answer: B

 

NEW QUESTION 203
......