Practice on 2023 LATEST C_IBP_2305 Exam Updated 86 Questions
Download Latest C_IBP_2305 Dumps with Authentic Real Exam QA's
NEW QUESTION # 31
You need to create time periods for the time profile in a planning area.What should you be aware of when running the Create Time Periods application job?
- A. A time profile has to be activated so that the application job can proceed.
- B. This application job can be run for multiple time profiles at once.
- C. In the Parameter Section of the application job, choose the Time Profile ID and Planning Area.
- D. The assigned Planning Area must be active.
Answer: C
NEW QUESTION # 32
Model configuration allows the attributes of a master data type to be assigned as key figures.Which features are relevant for this type of object?
- A. This object provides a single value for a unique planning combination.
- B. This object contains user-defined criteria that monitor the running of business plans.
- C. This object is not exposed to the user in planning views or modeling.
- D. This type of key figure is not usually stored and it cannot be set to editable.
Answer: A
NEW QUESTION # 33
How can the SAP IBP scenario modeling functionality support business users in the S&OP planning cycle?Note: There are 2 correct answers to this question.
- A. Simulate statistical forecast at the Demand Review stage
- B. Model inventory turns based on Target Safety stocks
- C. Simulate heuristics run in Supply Review stage
- D. Simulate demand sensing inputs for Supply Review
Answer: A,C
NEW QUESTION # 34
Safety Stock outputs from Multistage Inventory Optimization are sent to which of these processes? Note: There are 2 correct answers to this question.
- A. Supply Heuristics in SAP IBP for sales and operations
- B. Charts creation in SAP Supply Chain Control Tower
- C. Demand Sensing with Gradient Boosting (Full)
- D. Decoupling Points determination in SAP IBP for demand-driven replenishment
Answer: A,C
NEW QUESTION # 35
What are some of the properties of filter blocks?Note: There are 3 correct answers to this question.
- A. Filter blocks can be visualized in SAP IBP, add-in for Microsoft Excel
- B. Filter blocks can be visualized in the Key Figure Calculations app.
- C. Filter blocks are imposed when modeling attribute transformations.
- D. Filter blocks are imposed when modeling an attribute as a key figure.
- E. Filter blocks are imposed when modeling cross-period calculations.
Answer: A,C,D
NEW QUESTION # 36
SAP IBP ensures interoperability with which applications?Note: There are 2 correct answers to this question.
- A. Financial Planning in SAP Analytics Cloud
- B. Salesforce Sales Cloud
- C. User management in SAP Success Factors
- D. Business Network in SAP Ariba
Answer: A,D
NEW QUESTION # 37
Which processes are running in sample planning area SAPIBP1? Note: There are 3 correct answers to this question.
- A. Inventory Optimization
- B. Sales and Operations Planning
- C. Demand Sensing
- D. Supply and Allocation Planning
- E. Response Planning
Answer: A,B,C
NEW QUESTION # 38
Which of the following are examples of time-independent key figures?Note: There are 2 correct answers to this question.
- A. A special key figure marked as an aggregate key figure (aggregate constraint)
- B. A unit of measure key figure, such as UOM CONVERSION FACTOR
- C. A forecast metric key figure, such FCSTMAPE
- D. A currency conversion key figure, such as exchange rate
Answer: A,B
NEW QUESTION # 39
Which are the mandatory preconditions for an attribute that can be used for saving the segmentation results?Note: There are 2 correct answers to this question.
- A. The attribute belongs to a simple or compound master data type.
- B. The attribute should be a non-key attribute of the master data type.
- C. The attribute should be assigned to all planning levels.
- D. The Business Meaning of the attribute has been specified.
Answer: A,B
NEW QUESTION # 40
Which applications are present in the sample model SAPIBP1?Note: There are 3 correct answers to this question.
- A. Inventory Optimization
- B. Demand Driven Replenishment
- C. Sales and Operations Planning
- D. Demand Sensing
- E. Response Planning
Answer: A,C,D
NEW QUESTION # 41
What is a prerequisite for modeling outsourced manufacturers with production capacity using the Supply Optimizer?
- A. Use production lead times and offsets to manage components at the outsourced manufacturing location
- B. Model target inventory and stocks at the outsourced manufacturing location
- C. Ensure that the outsourced manufacturing locations have a separate subnetwork
- D. Model relative production costs across internal locations and outsourced manufacturing locations
Answer: D
NEW QUESTION # 42
You created a key figure and want to add calculations.Which of the following rules do you consider?Note: There are 2 correct answers to this question.
- A. Aggregation calculations using SUM or MAX functions must be based on a higher aggregation level.
- B. All key figure calculations have calculation inputs, which can be marked as stored or calculated.
- C. Key figures can be calculated across different planning levels.
- D. The calculation chain for a key figure must always result in a calculated key figure.
Answer: B,C
NEW QUESTION # 43
Which of the following data inputs, when increased, will always cause an increase in the safety stock outputs when the Global (multi-stage) Inventory Optimization operator is run?Note: There are 2 correct answers to this question.
- A. Holding Cost Percentage
- B. Target Service Level
- C. Minimum Lot Size
- D. Transportation Lead Time Error CV
Answer: B,C
NEW QUESTION # 44
Which of the following solutions should be satisfied with violations penalized by the objective function of the time-series supply optimizer? Note: There are 3 correct answers to this question. Not adhering to maximum transport values
- A. Not-fully satisfied demands
- B. Not respecting production capacity
- C. Violation of minimum resource utilization
- D. Violation of minimum aggregated inventory values
Answer: A,C,D
NEW QUESTION # 45
Which functional capabilities are included in SAP IBP for response and supply?Note: There are 2 correct answers to this question.
- A. Planning with Product Allocations
- B. Detailed Production Scheduling
- C. Gating Factors
- D. Analyze Supply Usage
Answer: C,D
NEW QUESTION # 46
Which of the following are features of lag-based snapshots?Note: There are 2 correct answers to this question.
- A. Target key figures for these snapshots must have lag as a root attribute in its base planning level.
- B. Target key figures for these snapshots are exposed to the user in planning views.
- C. Lag-based snapshots are created in the Configuration app for a fixed time range.
- D. The number of lag-based snapshots are limited to nine levels.
Answer: A,C
NEW QUESTION # 47
Which of the following data can be tracked using a change-history-enabled key figure?Note: There are 3 correct answers to this question.
- A. Scenario ID
- B. Key figure type
- C. Reason code
- D. Attributes
- E. Modified date
Answer: C,D,E
NEW QUESTION # 48
You need to define a new logic for a key figure to drive values from the PERPRODCUSTREGION level to the PERPRODCUST level.Which of the following configuration options are possible for this process?Note: There are 2 correct answers to this question.
- A. Splitting the values from aggregated to detailed level using multiplication by the proportions
- B. Splitting the values from aggregated to detailed level, based on the time profile attribute
- C. Splitting the values from aggregated to detailed level, based on a stored split-factor key figure
- D. Splitting the values from detailed to aggregated level by using a copy operator
Answer: A,C
NEW QUESTION # 49
You want to display and edit data in different Units of Measure (UOM).Which of the following must you consider before you use the UOM?Note: There are 3 correct answers to this question.
- A. Units of measure are usually not time-dependent.
- B. Conversion to the target unit of measure is handled by SAP IBP Excel UI
- C. Unit of measure is an attribute of a master data type, such as Product.
- D. Analytics provide the user with the option to select the target unit of measure.
- E. Units of measure are usually not time-independent.
Answer: A,C,D
NEW QUESTION # 50
You are working with inventory key figures.What are some of the business scenarios where you can use the Last Period Aggregation function?Note: There are 2 correct answers to this question.
- A. Search for and return the last not null value of the inventory key figure
- B. Calculating how many periods inventory is going to last based on the planned demand
- C. Calculating the value of inventory on a weekly basis, using static aggregation from the daily level
- D. Calculating the value of inventory on any time profile level ensuring flexibility of calculation
Answer: A,B
NEW QUESTION # 51
Which of the following are capabilities of the Manage Forecast Error Calculations - Inventory Optimization app?Note: There are 2 correct answers to this question.
- A. Adjust for forecast bias in Forecast Error CV calculations
- B. Adjust Safety Stock Recommendations based on forecast error CV input
- C. Propagate forecast error to upstream locations in a supply chain network
- D. Identifiy intermittent demand for Forecast Error CV calculations
Answer: A,B
NEW QUESTION # 52
For your project, you create a new planning area and consider how to create analytics and alerts for it.How can you create these objects?
- A. Merge analytics and alerts into a new planning area from any sample planning area.
- B. Use the option for copying analytics and alerts into the new planning area from the existing custom planning area.
- C. Use the option for copying analytics and alerts when creating a new planning area from the sample SAPIBP1.
- D. Create analytics and alerts in the new planning area from scratch using the Intelligent Visibility application.
Answer: C
NEW QUESTION # 53
You are working to realign the data due to a recent warehouse closure.What should you be aware of in regards to the realignment steps settings?Note: There are 2 correct answers to this question.
- A. You must mark the realignment step as "shared" and assign the steps to users.
- B. The name of the realignment step should be no longer than 20 characters.
- C. A realignment step can change master data, planning objects and key figures.
- D. The number of steps in the realignment run is limited to 255.
Answer: A,C
NEW QUESTION # 54
......
Authentic C_IBP_2305 Exam Dumps PDF - Aug-2023 Updated: https://pass4sure.examtorrent.com/C_IBP_2305-prep4sure-dumps.html