SAP C-TPLM22-67 Exam Syllabus Topics:
| Section | Weight | Objectives |
|---|---|---|
| Reporting | 8% | - Report Painter - Cost Center Reporting - Project Information System |
| Project Structures | >12% | - Milestones - Networks and Activities - Work Breakdown Structure (WBS) |
| Cost and Budgets | >12% | - Budget Management - Cost Reporting - Cost Planning |
| Revenues and Payments | 8–12% | - Billing and Settlement - Revenue Planning |
| Material | >12% | - WBS BOM - BOM-PS Interface - Material Procurement - Component Assignment |
| Dates | >12% | - Constraints and Dependencies - Scheduling Concepts - WBS and Network Scheduling |
| Resources | >12% | - Integration with HCM - Capacity Planning - Resource Planning |
C-TPLM22-67 Exam FAQ — Methods, Measurement, Mastery
The SAP Certified Application Associate - SAP Project Systems with SAP ERP 6.0 EHP7 exam contains 80 to complete within 180 minutes. Timed simulation in the ExamTorrent Desktop Test Engine teaches that rhythm before exam day does.
The official SAP Certified Application Associate - SAP Project Systems with SAP ERP 6.0 EHP7 outline defines 7 domains. The leading three are Resources (>12%), Dates (>12%), and Revenues and Payments (8–12%). The full list is in the topics section above, and ExamTorrent's 165 practice questions cover each one.
Online proctored or onsite at SAP authorized test centers Register for the SAP Certified Application Associate - SAP Project Systems with SAP ERP 6.0 EHP7 exam through these official channels:
After booking, ExamTorrent delivers your practice questions within 1 minute — preparation starts the same day.
The C-TPLM22-67 exam is a SAP certification exam validating the SAP Certified Application Associate - SAP Project Systems with SAP ERP 6.0 EHP7 syllabus shown above. It belongs to these credential paths: SAP Certified Application Associate - Project Systems. Candidates in 2026 start with ExamTorrent's 165 practice questions, available as a printable PDF, a Windows Desktop Test Engine, and an Online Test Engine — three versions of the same materials.
ExamTorrent issues a full refund if you take the SAP Certified Application Associate - SAP Project Systems with SAP ERP 6.0 EHP7 exam within 60 days of purchase and do not pass. The policy does not apply if the exam is taken within 3 days of purchase, if the exam was never actually taken, or to free materials or expired orders, and the candidate name must match the payer name. Submit a scan of your enrollment slip and the official Score Report PDF within 2 days of the exam; claims are processed within 7 days. Alternatively, exchange for two free exam products of equal value and keep your original update service. Orders arrive by email within 1 minute — contact support if nothing arrives within 2 hours.
The SAP Certified Application Associate - SAP Project Systems with SAP ERP 6.0 EHP7 exam requires 55% to pass, and registration costs USD 550–592. A failed attempt means paying the same fee again — a readiness check with the ExamTorrent engines before booking is the cheaper option.
No mandatory prerequisites; basic knowledge of SAP ERP and Project Systems recommended Since requirements change over time, confirm the latest on the official SAP exam page before scheduling.
SAP recommends these training resources for the SAP Certified Application Associate - SAP Project Systems with SAP ERP 6.0 EHP7 exam:
- PLM210: Project Structures in SAP PS
- PLM220: Project Execution in SAP PS
- PLM230: Project Cost and Budgeting in SAP PS
Follow the training with steady self-testing — the 165 practice questions from ExamTorrent help you apply theory and fill any gaps the training leaves.
Three versions of the same study materials: a printable, expert-prepared PDF with free demo download and instant access; a Desktop Test Engine for Windows with customizable simulation and timed modes that works offline; and an Online Test Engine for any browser on Windows, Mac, Android, and iOS with test history and performance review. All 165 practice questions are identical across versions. Every purchase includes 365 days of free updates, a 50% renewal discount afterward, and unlimited computer installations.
SAP Certified Application Associate - SAP Project Systems with SAP ERP 6.0 EHP7 Sample Questions:
In addition to manual planning in the WBS, you sometimes assign different types of orders (internal orders or maintenance orders, for example) to the WBS element that are flagged as account assignment elements. What is the use of this assignment?
There are 3 correct answers to this question.
Response:
- A. This assignment can then be used to display the unit costs of the orders of the project
- B. It can be copied to a new project
- C. Cost planning can be moved automatically along with the activities
- D. This assignment can then be used to display the planned costs of the orders of the project
Correct Answer: B,C,D 🗳️
Which of the following specifies how much time must elapse between individual archiving steps in network type?
Please choose the correct answer.
Response:
- A. Functional areas
- B. Functional areas
- C. Residence times
- D. Classification indicator
Correct Answer: C 🗳️
You have created a network with successive activities. After scheduling the network, the Gantt chart shows that every activity has the same earliest start and earliest finish date as the network header. What could be the reason?
Please choose the correct answer.
Response:
- A. The scheduling type is set to capacity requirements only.
- B. The normal duration of each activity is missing.
- C. The control key is set to no scheduling.
- D. There is a loop in the network.
Correct Answer: A 🗳️
You can maintain the following objects in the Project Builder. (4)
- A. Milestone
- B. Maintenance Order
- C. Network
- D. Internal Order
- E. Project definition
- F. Work Breakdown Structure
Correct Answer: A,C,E,F 🗳️
Which of the following related to an activity stipulates the activity type and determines how an activity is handled during calculation, scheduling and capacity planning?
Please choose the correct answer.
Response:
- A. Customizing key
- B. Control key
- C. Scheduling key
- D. Confirmation key
Correct Answer: B 🗳️